Name and address of organiza-tion
|
Name of works and services
|
Agreement period
|
1
|
“Falcon Oil and Gas Ltd.” LLP, Almaty city, Gogol st., 86
|
Project/program of elimination of company development consequences
|
29.05.2009
22.02.2010
|
2
|
“Arna Petroleum” LLP, Shymkent city, Tauke khan prospect, 51
|
Development of “The program of elimination of subsoil user “Arna Petroleum” LLP activity consequences on “Tastobe” contract area”
|
26.10.2009
22.02.2010
|
3
|
“Kazakhturkmunai” LLP, Aktobe city, Zhambil st., 104,
tel: +7 7132 21 53 00/01/02 21 00 34
|
The project of elimination of the fields Western Elmes, Northeast Saztobe, Southeast Saztobe and Laktybay development consequences with the “Assessment of Impact on Environment” project (EIA)
|
30.03.2009
|
4
|
JSC “SNPS Ay Dan Munay”, Kizilorda city, Zhibek st., 9,
tel: 8 (7242) 20 04 21
|
Development of the program of subsoil user activity consequence elimination on the contract area of the field “Blinovskoye” with the "Assessment of Impact on Environment" project (EIA)
|
11.08.2010
|
5
|
«ЕМЕ» LLP, Atyrau city, Temirkhanova st., 4 B
|
Development of the program of subsoil user activity consequence elimination with the "Assessment of Impact on Environment" project (EIA)
|
17.05.2010 17.10.2010
|
6
|
“Falcon Oil and Gas Ltd.” LLP, Almaty city, Shevchenko st., 90
|
EIA and technical projects.
|
25.07.2012 25.09.2012
|
7
|
“Arna Petroleum” LLP, Shymkent city, Tauke khan prospect, 51,
tel: +7 727 387 35 31, 387 37 23, 387 37 24
|
Construction of roads and exploratory wells boring platforms, within the block XXXVII – 12-A (partially), B (partially) on the territory of Mangistau oblast of the Republic of Kazakhstan, “Tastobe” section
|
10.07.2012 10.08.2012
|
8
|
“Kozhan” LLP, Almaty, Pirogov St. 31, 6 floor, office 600 B, tel.: 8 727 259-89-03/04, 8 712 235-43-30
|
Development of EIA and technical projects (field Morskoye, wells №52,53,54,25 with a depth of 1400m)
|
15.01.2013
|
9
|
“Falcon Oil and Gas Ltd.” LLP, Almaty city, Shevchenko st., 90
|
Determination of the coordinates of the well during the implementation of drilling program on the block Zharkamys West-1 in 2013
|
11.02.2013
|
10
|
“Kozhan” LLP, Almaty, Pirogov St. 31, 6 floor, office 600 B, tel.: 8 727 259-89-03/04, 8 712 235-43-30
|
The technical project on construction of directional well No. 35 with a project depth of 1750 m (down) in the contract area of the field “Dauletala”.
|
20.02.2013
|
11
|
“Falcon Oil and Gas Ltd.” LLP, Almaty city, Shevchenko st., 90
|
The group technical project on construction of vertical exploration well
|
18.04.2013
|
12
|
“Falcon Oil and Gas Ltd.” LLP, Almaty city, Shevchenko st., 90
|
The individual technical project on construction of directional exploration well
|
18.04.2013
|
13
|
“Firm Ada Oil” LLP, Almaty city, al-Farabi pros., 19/1 BC «Nurly tau», 5th floor
tel: 8 (727) 311 1521
|
Project of Customer activity consequences elimination
|
11.04.2013
|
14
|
JSC “TransNafta-Centre”, Almaty, al-Farabi ave., 7, BC "Nurly Tau", block 4A, 8 floor, оffice №34
tel: 8 (727) 2777-681
|
Development of technical projects (2 units)
|
07.06.2013
|
15
|
“TetisAralGaz” LLP
|
Group technical project
|
05.07.2013
|
16
|
The company “Alties Petroleum International B.V.”, Atyrau, Azattyk av., 78А
tel: (+007) 712 2 45-17-20
|
Group technical project
|
04.09.2013
|
17
|
JSC "Karazhambasmunay", Mangistau oblast, Aktau, 15-8
|
Development of technical projects
|
05.09.2013
|
18
|
Branch of the company "Jupiter Energy Pte.LTD", Mangistau oblast, Aktau, 15-70, tel: 8-7292-47-00-77
|
Development of the standard technical project for carrying out insulating and liquidating works for preservation and abandonment of wells of the fields Akkar North (Eastern Bloc), Akkar East, Zhetybai West
|
07.10.2013
|
19
|
"SCS Holding" LLP, Kizilorda city, Tazhibaev st., 23 «А»
|
The group technical project on construction of search - exploration wells with a depth of 2300m
|
24.12.2013
|
20
|
“Kazakhturkmunai” LLP, Aktobe city, Zhambil st., 104, tel: 8-7132-21-00-46
|
Development of the program of activity consequence elimination
|
11.03.2014
|
21
|
“Falcon Oil and Gas Ltd.” LLP, Almaty city, Shevchenko st., 90
|
- The individual technical project on construction of horizontal wells W-10 on the field Shoba (including EIA);
- The individual technical project on construction of The individual technical project on construction of horizontal wells W-11 on the field Shoba (including EIA);
- The individual technical project on construction of horizontal wells W-12 on the field Shoba (including EIA);
- The group technical project on construction of injection wells on the field Shoba (including EIA)
|
02.04.2014
|
22
|
“Falcon Oil and Gas Ltd.” LLP, Almaty city, Shevchenko st., 90
|
Development the group technical project and EIA for the construction of wells on the structure Kiyaktysay North
|
09.04.2014
|
23
|
JSC “Turgai Petroleum”, Kyzylorda city, Esenova st.,1А, tel: 8-7242-27-81-41
|
Development of the standard project for conservation, elimination and depreservation of wells of the fields Kumkol and East Kumkol
|
11.04.2014
|